Level 4 Pickleball Court

Quote review & market benchmark — enter the access code.

Level 4 Pickleball Court

Two quotes from Chew A.M. (NC Singapore / Elitez FMCG), dated 1 and 7 September 2026, benchmarked line by line against the bands on your Unit Cost Reference and against fresh market research. ← Back to tracker

$148.8kBoth quotes, before GST
$162.2kIncluding 9% GST
~$20.6kIdentified negotiating room
0Sports floor quoted

The headline

read this first
These two quotes total $148,825.80 but they do not deliver a playable court. The builder’s quote hacks off the old screed and relevels 468m² to a bare cement finish — and stops there. There is no sports surface, no line marking, no net posts and no barrier netting in either document. What you are buying is an excellent floor slab, a glazed refreshment room and a very well-lit, well-ventilated empty hall.
The pricing itself is mostly good. Fourteen of the twenty-three measured lines sit at or below the market median you already established, and several are materially cheaper than what NC quoted you for identical work on the main 505 fit-out — the 100A distribution board is 34.8% cheaper, the framed glass 30% cheaper, the brickwork 31.5% cheaper. The rescreed, at $3.97/ft², is below the Singapore market floor. Chew has sharpened his pencil on this one.
The money is concentrated in two lines. The four HVLS fans ($35,100) and the preliminaries ($9,562.50) together are $44,662.50 — 30% of the whole job — and both are the kind of line that is priced by judgement rather than measurement. The fans are explicitly a provisional sum. That is where the negotiation is, and it is worth roughly $17,000 of the ~$20,600 total room identified below.
1

⚡ Electrical Installation

11 items · $74,357.55
Ref NCS/QUO/26/08-ELE-PBC, dated 1 Sep 2026, to Elitez FMCG (attn. Eevann). Chew’s covering email states the quantities are still to be confirmed, so treat every count here as provisional — the rates are what you are agreeing, not the totals. Note also that the quote skips from item 3 to item 5: there is no S/N 4, which may simply be a numbering slip or may be a dropped line.

Lighting point (wiring, concealed)

REVIEW
$70180 /pt commercial
$123.75 × 75
$55

Sits almost exactly on the median of the band already established on the reference page — and it is 6.4% cheaper than the $132.25 NC quoted for the same item on the main 505 fit-out. Hard to attack on rate; attack the count instead (75 wiring points plus 130 track points plus 80 spotlights is a great deal of lighting for one hall).

Twin pickleball court LED spotlight

REVIEW
$250450 /luminaire est.
$360.00 × 20

This band is an approximation. No directly comparable sports-luminaire rate exists in the reference set, so it is estimated from commercial floodlight pricing and should be treated as indicative until NC supplies the photometric data sheet. Ask for the design lux at floor level: recreational pickleball wants around 500 lux, competitive play 750+. Twenty luminaires is the right order of magnitude for two courts.

Track fitting (networking, refreshment, cheering)

REVIEW
$55105 /fitting
$45.00 × 130
$65

Below the floor of the fitting supply-and-install band, and well under the $69–$86.25 NC charged on the main quote. This one is genuinely good — bank it and do not reopen it.

LED 12W spotlight (clips to track)

REVIEW
$55105 /fitting
$39.38 × 80

Also below the band floor. A track head at $39.38 supplied and clipped on is competitive. Bank it.

LED exit / emergency fitting

REVIEW
$55105 /fitting
$84.38 × 25

Upper-middle of the fitting band, which is normal for exit and emergency luminaires — they carry battery packs and need SCDF-compliant spec. Not a lever.

2×13A double socket

REVIEW
$100150 /pt commercial top
$151.88 × 30
$65

Just over the top of the commercial band, though 8.9% better than the $166.75 on the main quote. Thirty points makes this a modest lever — landing it at $125 (the band median) recovers about $806.

32A TPN isolator (aircon)

REVIEW
$250650 /unit
$562.50 × 2

Not like-for-like with the $100–500 20A DP isolator band on the reference page — a 32A triple-pole-and-neutral device is physically larger and needs heavier tails, so the band is widened accordingly. Upper half, but only two units, so worth about $225 at most.

20A isolator + control cable (HVLS fans)

REVIEW
$100500 /unit
$427.50 × 4
$150

12.6% higher than the $379.50 NC charged for a 20A DP isolator on the main quote, though this one includes the control cable run from fan to switch. Ask what that cable adds — if it is under $50, the isolator itself is being priced above NC's own precedent.

HVLS DC fan, 5.5m diameter, 5-yr warranty

REVIEW
$4,0006,500 /fan supplied+installed
$8,775.00 × 4

The single biggest line in either quote — $35,100, or 47.2% of the entire electrical bill — and NC's own footnote calls it a provisional sum, which is an open invitation to re-price it. The bracket: a 5.5m HVLS ex-China lists at US$900/unit at 1–9 pieces (AC gear motor, 12-month warranty); Western branded units run past US$10,000 at 20–24ft before installation. NC's unit is a DC/PMSM motor with a 5-year warranty, which legitimately sits well above the China price — but Singapore has at least four established HVLS suppliers (Spacefans, Evel, Coomi, Temet). Get three direct quotes and convert the provisional sum into a fixed price.

100A DB for pickleball & recreation area

REVIEW
$2,5004,500 lump build-up
$3,150.00 × 1
$1,500

Below the median, and 34.8% cheaper than the $4,830 NC quoted for a 100A board on the main fit-out. Genuinely improved pricing. Bank it.

Sub-main, 35mm² XLPE + 16mm² earth

REVIEW
$100115 /m
$1,125.00 lump

The run length is not stated. At the ~$107/m rate established on the reference page, $1,125 implies roughly a 10.5m run from the existing 400A MSB. If the actual run is longer, this is cheap; if much shorter, it is not. Ask for the length before accepting.

💡 Where the electrical money actually is: the four HVLS fans are 47.2% of this quote on their own. Everything else combined — 330 lighting and power points, a new 100A board and a sub-main — comes to $39,257.55. Fix the fans and you have fixed this quote.
2

🧱 Builder’s Work & Air-Conditioning

12 items · $74,468.25
Ref NC/CAM/505/L4-PBC/2026/001, dated 7 Sep 2026. Note 1 of this quote excludes all M&E services unless separately listed — which is what makes the scope gaps below load-bearing rather than pedantic.

Hack existing de-bonded screed + offsite disposal

REVIEW
$2748 /m²
$28.13 × 468 m²

At the bottom of the screed-removal band ($2.61/ft²). Includes offsite disposal, which is the expensive half of this trade in an industrial building with lift constraints. Bank it.

Clean, wash + one coat bonding agent

REVIEW
$26 /m²
$2.81 × 468 m²

$1,316 in total. The correct preparation step before a rescreed, priced as a token. Not worth a conversation.

Rescreed floor to level

REVIEW
$53.8096.90 /m² SG levelling
$42.75 × 468 m²

The most important number to get right, and NC is well under market. Singapore floor levelling ahead of a vinyl finish runs S$5–9/ft² ($53.80–96.90/m²); NC is at $3.97/ft². Note that the reference page's $21.50–43/m² screed band is not comparable — that is 3–4mm self-levelling compound, not a full 468m² structural rescreed. At $20,007 this is the second-largest line in either quote and it is priced below the market floor. Do not touch it.

Vinyl floor tile to refreshment room

REVIEW
$48108 /m² supplied+installed
$61.88 × 60 m²
$35.50

The same $61.88/m² NC used for carpet tile on the main quote, applied here to vinyl. Comfortably in the lower half of the resilient-flooring band. Fine.

1.0m brick wall + plaster both sides

REVIEW
$130210 /m²
$157.50 × 9 m²
$150

31.5% cheaper than the $230/m² NC quoted for curved brickwork on the main fit-out — straight runs are simpler and the pricing reflects that honestly. Below the band median. Bank it.

Fixed glass panel, 13.52mm laminated

REVIEW
$3555 /ft² framed
$562.50/m² = $52.26/ft²
$12.50

A 30% improvement on the ~$75/ft² NC charged for framed laminated glass on the main quote, and now inside the band. One small point: the panel is described as 9.0m × 1.2m = 10.8m², but billed at 11m² — a 1.85% round-up worth $115. Trivial in itself, but it tells you the quantities are rounded rather than measured.

100mm drywall partition above glass

REVIEW
$100107 /m²
$101.25 × 30 m²
$50

Essentially on the band floor, and within $2/m² of the $103.50 NC quoted on the main fit-out. Consistent pricing. Not a lever.

E/O mild-steel frame support

REVIEW
$54117 /m
$90.00 × 23.5 m
$70

21.7% cheaper than the $115/m NC quoted for steel stiffener posts on the main quote, and mid-band. Reasonable for framing that has to carry a 9m glass run with drywall above it.

Glass door, 1.0m W × 2.2m H

REVIEW
$1,7002,100 /leaf
$1,856.25 × 1
$850

13.2% below the $2,137.50 NC quoted per leaf on the main fit-out, and just under the band median. Fair for an aluminium-framed laminated leaf. Bank it.

Dry pantry cabinet + 50mm plinth (h ≤ 3.0m)

REVIEW
$210400 /ft run
$1,462.50/m = $445.78/ft
$150

Above the top of the full-height carpentry band. The 3.0m height does justify a premium — roughly 25% more material than a standard 2.4m wardrobe, so the height-adjusted equivalent is about $356/ft, still above the $305 median. Across a 5.5m run, landing this at $400/ft recovers about $828. A real but modest lever.

Relocate 2 aircon units + chemical wash + repipe

REVIEW
$1,5002,500 /unit
$2,025.00 × 2

Band estimated for commercial relocation including chemical wash to both condenser and fan-coil, new refrigerant piping, insulation, PVC trunking and drainage. NC lands on the median. Note this quote is copied to Natural Cool — the aircon arm — so the relocation is being done in-house rather than subcontracted.

Preliminaries, supervision, transport, scissor lift

REVIEW
$3,2457,789 lump (5–12% of works)
$9,562.50 lump

The softest number in either quote. At $9,562.50 against $64,905.75 of measured works this is 14.7%, where Singapore fit-out preliminaries typically run 5–12%. It also echoes the main 505 quote, where NC charged $13,075 across supervision, scaffolding and documentation for work the previous CT Hub contractor did free of charge — a pattern your own margin note already flagged. The scissor lift inside this line is a genuine cost (roughly $800–1,500/month hire); the supervision element is where the negotiation sits. Landing at 10% recovers about $3,072.

💡 Eight of these twelve lines are at or below the market median. The two to work on are the pantry cabinet and the preliminaries; everything else is either fairly priced or actively good. Pushing hard across the whole sheet would be reading this quote wrongly.
3

⚠ What is missing

the expensive part

Costs below are indicative market ranges researched for this review, not quotes. They are what you should expect to add on top of the $148,825.80 — and the first one has a sequencing trap attached to it.

Sports floor finish

S$4,600 – 47,300

Neither quote includes a playing surface. Acrylic at 4mm runs US$21–64/m²; cushioned PU at 8mm runs US$43–107/m²; PVC roll from a Singapore supplier typically lands S$45–90/m² installed. The spread depends entirely on system and court count. Singapore suppliers who do exactly this: GymFlooring.sg, Kohup Sports, Pickleball Corner SG.

Net posts & nets — sequencing trap

S$600 – 1,500 / court

Resolve this before the rescreed is poured. If the posts are in-ground rather than portable, their floor sockets must be set into the new screed. Miss it and you are hacking into a brand-new 468m² floor you have just paid $20,007 for.

Line marking

S$800 – 2,000 / court

Non-fading court paint to the 20ft × 44ft playing layout. Normally bundled with the surfacing contractor, which is another reason to appoint one before the floor is finished.

Perimeter netting / divider curtain

S$3,000 – 10,000

Essential if two courts share the hall with a refreshment and networking area — otherwise balls run into the social space continuously. Not mentioned anywhere in either quote.

CCTV & Wi-Fi

Explicitly excluded

Note (f) of the electrical quote carves both out. For a bookable court you will want at least Wi-Fi coverage and probably cameras.

L4 DB & solar inverter diversion

Explicitly excluded

Note (e) carves out diverting the existing Level 4 distribution boards and the solar panel inverter. If either sits in the court footprint this becomes a real and awkward cost.

Realistic all-in. $148,825.80 of quoted work, plus roughly $10,000–60,000 of unquoted court-specific scope, plus 9% GST. Budget $175,000–230,000 for a finished, playable, two-court facility — and get the surfacing contractor appointed before NC pours the new screed.
4

📊 Totals & identified room

arithmetic checked
QuoteReferenceDatedAmount
Electrical installationNCS/QUO/26/08-ELE-PBC1 Sep 2026$74,357.55
Builder’s work & air-conditioningNC/CAM/505/L4-PBC/2026/0017 Sep 2026$74,468.25
Subtotal before GST$148,825.80
GST @ 9%$13,394.32
Total payable as quoted$162,220.12

Both quotes add up correctly — every line was recomputed and every extension matches. Payment terms are identical on both: 30% on order, 25% on delivery of materials, 40% on completion, 5% on handover. Both are valid 30 days, so the electrical quote lapses 1 October and the builder’s 7 October 2026. The electrical quote is additionally pegged to an LME copper base of US$14,300.

Where the room isFromToRecovers
HVLS fans — provisional sum, re-tender$8,775/fan~$5,250/fan$14,100
Preliminaries & supervision14.7% of works10%$3,072
Dry pantry cabinet$445.78/ft$400/ft$828
2×13A double sockets × 30$151.88$125$806
Lighting points × 75$123.75$110$1,031
20A HVLS isolators × 4$427.50$300$510
32A TPN isolators × 2$562.50$450$225
Total identified room13.8% of pre-GST$20,572

Deliberately excluded from this table: the rescreed, the hacking, the glass, the brickwork, the drywall, the steel framing, the glass door, the track fittings and the 100A board. All nine are at or below market and several are materially better than NC’s own precedent pricing. Pushing on them would cost you credibility on the two lines that actually matter.

5

❓ Put these to Chew before you negotiate

7 questions
  1. How many courts does 468m² actually deliver?Neither quote says. Item 2 of the electrical quote describes a “twin pickleball court” spotlight, which implies two — but at the minimum 9.1 × 18.3m footprint two courts consume 333m², leaving only 135m² for refreshment, networking, storage and two toilets. The 60m² of vinyl to the refreshment room suggests the social area is smaller than that. Get the layout confirmed on a drawing.
  2. What is the design lux at floor level?Recreational play wants roughly 500 lux, competitive 750+. Twenty court luminaires at $360 each is a $7,200 commitment made without a photometric calculation on the table.
  3. Are the net posts in-ground or portable?The single highest-consequence question here. In-ground sockets must be cast into the new screed — deciding after the pour means hacking a new floor.
  4. What is the sub-main run length?$1,125 for 35mm² XLPE implies about 10.5m at market rate. Confirm the distance from the existing 400A MSB.
  5. Why is there no S/N 4 in the electrical quote?The schedule runs 1, 2, 3, 5, 6… A dropped line that reappears later as a variation order is exactly what note (a) allows.
  6. Will you fix the HVLS price?It is flagged as a provisional sum. Ask for a fixed price against a named make and model, with the 5-year warranty documented — and mention you are getting comparison quotes.
  7. Do you need four 5.5m fans in an air-conditioned hall?Two existing aircon units are being relocated into this space. Four HVLS fans and mechanical cooling may be over-specified — dropping to two fans saves $17,550 outright before any rate negotiation.
6

🤝 How to play it

with Mr. Chew
Open by banking the wins, out loud. Fourteen of the twenty-three lines are at or below the market median, and several beat his own pricing on the main 505 job. Say so specifically — the 100A board, the glass, the brickwork, the rescreed. It costs nothing, it is true, and it establishes that your numbers are researched rather than reflexive. It also makes the two lines you do push on impossible to dismiss as haggling.
Then go to the fans, and only the fans. They are 47.2% of the electrical quote, they are a declared provisional sum, and Singapore has four established HVLS suppliers you can name. This is not an attack on his pricing — it is taking him up on the provisional-sum invitation he wrote himself.
Ask the fan-count question before the fan-price question. Four fans in a hall that is also getting relocated air-conditioning is the more valuable challenge: dropping to two saves $17,550 with no rate negotiation at all, and it is a design conversation rather than a commercial one.
Preliminaries last, and framed as a package. 14.7% against a 5–12% norm, on top of the $13,075 of supervision on the main quote. Offer to settle preliminaries across both the 505 fit-out and this job in one number — you already have significant work with him, and a combined figure is easier for him to concede than a line-item cut.
Raise the missing scope as a shared problem, not a gotcha. He quoted exactly what was asked of him. But the court is unplayable as specified, and the net-post sequencing genuinely threatens the floor he is about to build. Bringing him the surfacing question early makes him an ally on it — and he may well have a surfacing subcontractor worth using.

Sources: both NC quotations (1 & 7 Sep 2026) · Chew A.M. covering email, 7 Sep 2026 · Unit Cost Reference bands · Singapore screed and fit-out rate guides · HVLS supplier pricing (made-in-china.com, humongousfan.com) · pickleballcourtco.com Singapore facility guide · gymflooring.sg · HardwareZone forums · sportsvenuecalculator.com
Market bands are editable — click any figure to change it and the median, variance and verdict recompute and save.